Ep 24: Why Your Contractor Wants Paid Before Your Lender Does
You have $40,000 of approved rehab money sitting right there. So why can't you touch a dime of it on day one?
A flipper closes on a house, the loan is funded, and they feel great. About a week later they are sweating over money they were told they had. Funded means two different things, and nobody explains the second one.
The purchase funds at closing. The rehab money sits in a holdback and comes out in pieces as the work gets done. On day three the contractor wants a check for work that has started, and the lender wants proof of work that is finished. That gap is where first-timers get squeezed.
Neil Timmins and Maggie Monroe walk through a Merle Hay ranch with a $40,000 rehab split into four draws, where the first two add up to $22,000 right when your cash is thinnest. Neil also tells the story of a four-line scope that listed "General Remodel, $22,000," and what happened when he pressed on it.
In This Episode, You'll Learn:
- How to split a rehab budget into draw milestones before the loan closes
- How to cover the cash gap before your first draw clears
- How to tie your contractor's payments to the same milestones as your lender's releases
- How to write a scope that turns each draw into a ten-minute job instead of an argument
- How to submit a clean draw request the day a milestone is done
- And more.
Hosted by Iowa real estate investor Neil Timmins.
Want the written breakdown? Our article, Hard Money Draw Schedule Iowa: How Rehab Funds Get Released, is at https://littleguyloans.com
Find every episode at https://www.flippingiowa.com
Ready to fund your next flip? Little Guy Loans gets Iowa house flippers fast, flexible financing. Get funded today.
Flipping Iowa
Episode: 24
Title: Why Your Contractor Wants Paid Before Your Lender Does
[NEIL] Forty thousand dollars of rehab money. Approved, set aside, sitting right there. And on day one of the job, you can't touch a dime of it.
[MAGGIE] That sounds like a problem.
[NEIL] It's not a problem. It's how the whole thing is built. First-timers just don't find that out until the contractor is standing in the driveway with his hand out.
[MAGGIE] Okay. We're going to fix that today.
[MAGGIE] Welcome back to Flipping Iowa. I'm Maggie Monroe, and Neil, I want to start with something that keeps coming up. A flipper closes on a house, the loan is funded, they feel great. And then about a week later they're sweating over money they were told they had. How does that happen?
[NEIL] Because "funded" means two different things, and nobody explains the second one. The purchase funds at closing. The rehab money doesn't go out the door. It sits in a holdback and comes out in pieces as the work gets done.
[MAGGIE] Pieces. Meaning draws.
[NEIL] Draws. Same word, different meaning than the one people hear on the street. A draw is a release of rehab money after a stage of the project is finished and somebody has confirmed it's finished.
[MAGGIE] And for anyone just tuning in, this is Neil Timmins, the guy who runs Little Guy Loans. Littleguyloans.com if you want to find him. But today he's not pitching anything. He's the guy who has watched a lot of Iowa flippers get squeezed in this exact spot.
[NEIL] More than I'd like to admit. And it's almost always avoidable.
[MAGGIE] So here's my plan. We walk through how a draw schedule actually runs, what triggers each release, how to line up your contractor and your cash around it, and where it goes wrong. Sound fair?
[NEIL] Sounds fair. Let's start with the squeeze, because that's what gets people.
[MAGGIE] Walk me through the squeeze. Day three of the rehab. What's happening?
[NEIL] Day three. The contractor has mobilized. He's pulled a dumpster, he's bought some materials, maybe he's paid a demo crew. And he's looking at you for a check. Meanwhile your lender is saying, show me the work first, then I'll release money.
[MAGGIE] So the contractor wants money for work that's started, and the lender wants proof of work that's finished.
[NEIL] That gap in the middle is where first-timers get squeezed. Nobody did anything wrong. The timing just doesn't line up unless you plan for it.
[MAGGIE] Let me restate that, because I think it's the part people miss. If you walk into a rehab assuming the money flows the minute the work starts, you're going to be covering costs out of your own pocket for a while. Does that actually happen?
[NEIL] Every week. Somebody thinks the holdback is a checking account. It's not. It's a pacing tool. Money goes out against finished work, not promised work.
[MAGGIE] Why do lenders do it that way? Is it just caution?
[NEIL] Partly. But it protects you too. If every dollar went out at closing, your contractor could get way ahead of the progress, and you'd be the one holding a half-finished house and no money left. The draw keeps the money and the work moving together.
[MAGGIE] So the contractor can't take the money and run.
[NEIL] Or just wander off. That happens, and we'll get to it.
[MAGGIE] Okay, so what does the rhythm look like? Give me the loop.
[NEIL] Five steps, and it's almost always the same. One, closing. The purchase funds, and the rehab budget gets set aside. Two, work starts. Your contractor mobilizes, and the early costs usually land on you or on him until that first draw clears. Three, you submit a draw request. Photos, invoices, or a pay request from the contractor for the completed work. Four, verification. The lender checks it, either with an inspection or by reviewing photos. Five, release. Approved money goes to you or straight to the contractor.
[MAGGIE] And then you do it again.
[NEIL] Until the punch list is done. Most fix and flip loans run somewhere around three to five draws, depending on how big the rehab is and how you carve up the scope.
[MAGGIE] Does every lender run it exactly like that?
[NEIL] The rhythm is the same, the details live in your loan documents. So read them before you sign. I'd rather you hear that from me now than at the closing table, when you're tired and everybody's waiting on you.
[MAGGIE] That feels like advice that applies to a lot more than draws.
[NEIL] It applies to everything. But draws are where it bites.
[MAGGIE] Now, what actually triggers a draw? Is it a date? Is it a percentage?
[NEIL] It's milestones. Finished stages of work. Lenders want to see that the money already released turned into something real in the house.
[MAGGIE] Give me the typical stack.
[NEIL] First stage is demo and structural repairs, and anything that has to happen before walls close up. Second, rough-in work. Plumbing, electrical, HVAC, passed by the city inspector where that's required. Third, drywall, windows, doors, exterior. Fourth, kitchen, baths, flooring, fixtures. Fifth, paint, trim, the final punch list, and cleanup.
[MAGGIE] That's a pretty natural order. It's basically the order you'd do the work anyway.
[NEIL] That's the point. A good draw schedule isn't something the lender invents to slow you down. It follows how a house actually gets built. If your schedule fights the construction sequence, something's wrong with the schedule.
[MAGGIE] So what makes it smooth versus miserable?
[NEIL] One thing. Your scope of work. If it's line by line with a dollar amount on every line, splitting it into draws takes about ten minutes. If it's a one-page guess, every single draw turns into an argument.
[MAGGIE] That's a big claim. Ten minutes versus an argument.
[NEIL] I've seen both. And the argument is never really about the draw. It's about the fact that nobody defined the work.
[MAGGIE] Let's make this concrete. Pick a house.
[NEIL] Okay. A nineteen fifties ranch in Merle Hay. Forty thousand dollar rehab budget. New kitchen, two refreshed baths, new flooring throughout, an updated electrical panel, new windows, paint. Just a regular Des Moines metro flip.
[MAGGIE] And this is an illustration, not a quote on anybody's loan.
[NEIL] Right. Just a way to think about it. Here's one way the dollars could line up against milestones. Draw one, ten thousand. Demo, the electrical panel, rough-in work. Draw two, twelve thousand. Windows, drywall repairs, passed rough-in inspections. Draw three, ten thousand. Kitchen, baths, and flooring. Draw four, eight thousand. Paint, trim, fixtures, and the final punch list.
[MAGGIE] Okay, so four draws, and the first two add up to twenty-two thousand.
[NEIL] More than half the budget, in the first two draws. Notice what that does. Each draw matches a chunk of work you can photograph and point to. And the biggest costs, the ones that take real cash up front, show up early.
[MAGGIE] Which is exactly when your cash is thinnest.
[NEIL] Exactly when your cash is thinnest. The electrical panel, the windows, those aren't cheap, and they happen before you've gotten much money back.
[MAGGIE] So if I'm hearing you right, the front end of the schedule is where the stress lives.
[NEIL] That's where I'd spend my planning time. Not on draw four. Draw four is paint.
[MAGGIE] Draw four is paint. I'm putting that on a sign.
[MAGGIE] So how do you plan around the gap? Because draws reimburse work that's already done. There's a lag between spending and getting paid.
[NEIL] There's always a lag. If your contractor needs a deposit and materials on day one, somebody has to cover that before draw one clears. The question is whether you planned for who.
[MAGGIE] And the answer can't be "I'll figure it out."
[NEIL] That's the answer most people give. Here's what works instead. First, negotiate your contractor's payment schedule so it mirrors the draw milestones. If the lender releases money when the rough-in passes, the contractor's second payment should be tied to the rough-in passing. Same trigger, same day.
[MAGGIE] That makes sense. Everyone's looking at the same finish line.
[NEIL] Second, keep a cash cushion in reserve for the first stage of work. Not a fortune. Enough to cover that first stretch without borrowing from your grocery money.
[MAGGIE] Third?
[NEIL] Submit the draw request the day the milestone is done. Clean photos, invoices attached. Don't let it sit for a week because you were busy at your other job. Every day you wait is a day your contractor's waiting on you.
[MAGGIE] And I'd guess clean matters. Blurry photos, missing invoices.
[NEIL] Clean matters a lot. A draw request that needs three follow-ups takes three times as long. And fourth, keep a running sheet. Budget against actual spend, line by line. A draw should never surprise you.
[MAGGIE] The loan covers a lot, but it doesn't take over managing cash flow on the job.
[NEIL] Well said. It covers the money. It doesn't cover the discipline.
[MAGGIE] Neil, I want to push on the scope of work for a second, because you keep coming back to it. Is that really the thing that makes or breaks a draw schedule?
[NEIL] It is. And I can tell you why with a story, because a scope of work will tell you how advanced an investor is before you ever visit the property or check a reference.
[MAGGIE] Before you check a reference. That's a strong statement.
[NEIL] It's hard to fake expertise in the details. We got a scope from an investor who had told us he'd done a number of properties. I'll note that zero is a number too. The scope had about four line items on it. And one of them read, General Remodel, twenty-two thousand dollars.
[MAGGIE] General Remodel.
[NEIL] That's all it said. I have no idea what General Remodel means. It's not a trade. It's not a system. It's not a task. It's a placeholder for everything he hadn't figured out yet.
[MAGGIE] Okay, so what happened when you asked him about it?
[NEIL] I asked what specifically was going to be done. And the answer was, essentially, remodel the house. Which I understood. But that's not a scope. That's a budget guess wrapped in two words.
[MAGGIE] And that matters for draws because?
[NEIL] Because how do you split twenty-two thousand dollars of General Remodel into milestones? What's finished at the halfway point? Nobody can say. There's nothing to photograph, nothing to inspect, nothing to point at. Every draw on that line becomes a negotiation.
[MAGGIE] So it's not just a lender problem. It's his problem. He couldn't plan his own cash.
[NEIL] That's the part he hadn't thought about. The best investors, the ones who execute at a high level, send us scopes with ten to thirty line items. Flooring by room. Cabinets and countertops as separate lines. Electrical panel versus outlets versus fixtures. Plumbing rough-in versus fixtures. They know what's being done, who's doing it, when it's scheduled, and what it costs.
[MAGGIE] Did you lecture him?
[NEIL] No. It was a real conversation. Just a walk through what we needed to see and why. He went back to his contractor and broke it down line by line. And in the process, he found about fifteen hundred dollars in savings.
[MAGGIE] Was the contractor padding the number?
[NEIL] Not at all. That's the interesting part. When you ask the next series of questions, you find out what's actually required versus what everybody assumed. That fifteen hundred was sitting in the gap between a vague number and a specific one. It only came out because somebody pressed.
[MAGGIE] So if your scope is four lines, your draw schedule is a guess, and your budget is a guess too. Is that fair?
[NEIL] That's fair. A four-line scope isn't a plan. The discipline of breaking a rehab into line items forces you to understand the project before it starts, which is the only time that understanding is free.
[MAGGIE] I like that. Understanding is free before the project starts.
[NEIL] And expensive halfway through.
[MAGGIE] Okay, we're back. Neil, let's talk about the number that sits underneath all of this, because the draw schedule lives inside the bigger loan structure. What are the actual terms?
[NEIL] For our borrowers, up to ninety percent of the purchase price, that's loan to cost. Up to one hundred percent of the rehab costs. And a maximum of seventy percent of after repair value, which is the controlling cap.
[MAGGIE] The controlling cap. Meaning if the other two numbers add up to more, the cap wins.
[NEIL] Right. That last number decides how much total money is available. The draws are just how the rehab portion of it gets to the job. If the purchase plus the rehab runs past seventy percent of after repair value, the cap limits the loan and you cover the difference.
[MAGGIE] Which is something you want to know before you make an offer.
[NEIL] Before you make an offer. Run it on the front end, so you know your draw budget is real. I've seen people plan a whole schedule around money the cap was never going to allow.
[MAGGIE] And the approval and closing timeline? Because planning a schedule usually starts when you know when the loan funds.
[NEIL] Twenty-four hour approval, and we can close in as little as five days. So the clock on your first draw starts quicker than most people expect. Which is another reason to have the scope done before you apply, not after.
[MAGGIE] Let me ask the obvious follow-up. Where do people get this wrong? Besides the scope.
[NEIL] Three places. They don't read the loan documents. They don't tie the contractor's payments to the draw milestones. And they don't keep cash in reserve for stage one. Do those three things and draws stop being stressful. They turn into a routine.
[MAGGIE] A routine you can run on every deal.
[NEIL] Cosmetic refresh or full gut. Same loop.
[MAGGIE] Let me bring a listener's objection, because I think a lot of flippers are thinking this. Isn't this a lot of babysitting? I'm paying a contractor to run the job. Why am I doing paperwork every time he finishes a stage?
[NEIL] I hear it. And I get why it feels like homework. But think about what the paperwork is. Photos and invoices of work that's done. That's a record of your own project. If a dispute ever comes up, you've got a dated trail.
[MAGGIE] So it's protection for the investor, not just a hoop.
[NEIL] And honestly, it's the thing that separates the investors who scale from the ones who stay stuck. The ones doing a dozen flips a year aren't winging it. They've got a system, and the draw request is part of the system.
[MAGGIE] What about the flipper who says, my contractor and I go way back, I trust him?
[NEIL] Trust him. And still tie the money to finished work. Those two things don't fight each other. The best contractor relationships I've seen are the ones where payment terms were clear on day one, because nobody has to wonder about anything.
[MAGGIE] Clear is kind.
[NEIL] Clear is kind. And it's cheaper.
[MAGGIE] One more. What if the draw gets delayed? An inspection doesn't happen on time, the photos get kicked back.
[NEIL] That's why the cash cushion exists. And it's why you submit clean and early. If you build in a few days of slack, a delay is an annoyance. If you've got no slack, a delay is a crisis, and your contractor starts looking at other jobs.
[MAGGIE] Slack. Not glamorous, but it works.
[NEIL] Slack is underrated in this business.
[MAGGIE] Before we wrap up, we've got our little slice of Iowa history. And Neil, this one is right in our backyard.
[NEIL] Terrace Hill. The big hilltop mansion in Des Moines that's now the governor's residence.
[MAGGIE] I've driven past it a hundred times and never really thought about the money side.
[NEIL] It cost about two hundred fifty thousand dollars to build, between 1866 and 1869. And that price covered the carriage house, the furnishings, and roughly thirty acres.
[MAGGIE] That's a lot of money for the late 1860s.
[NEIL] A lot of money anywhere. The builder, a man named B.F. Allen, lost his fortune. And in 1884, a local businessman named F.M. Hubbell bought the place for sixty thousand dollars.
[MAGGIE] Sixty thousand. For all of it?
[NEIL] That's a quarter on the dollar for a mansion. And every flipper knows exactly what a motivated seller does to a price.
[MAGGIE] That one feels like it belongs on a whiteboard in your office.
[NEIL] Some version of it already is.
[MAGGIE] Okay. Let's land this. If somebody remembers only a few things from today, what are they?
[NEIL] Three. One, a draw releases money against finished work, so plan your cash for the gap before draw one lands. Two, your scope of work is the whole game. Line by line, a dollar on every line, and split into milestones before the loan closes. Three, tie your contractor's payments to the same milestones, so everybody's looking at the same finish line.
[MAGGIE] And read the loan documents.
[NEIL] And read the loan documents. Everything else is steady work. Keep your photos and invoices clean, keep your running sheet current, and a draw schedule stops being a hurdle and starts being a pacing tool.
[MAGGIE] I'd add one thing. The money arrives as the work gets done, and that keeps the budget honest. That's not a restriction. That's help.
[NEIL] That's the right way to see it.
[MAGGIE] Neil, thanks for walking through this one.
[NEIL] Thanks, Maggie. Good questions, as always.