Most flippers build the budget around cabinets, flooring, and paint, then push permits to the bottom of the list. The city does not usually kill the deal. Finding out about the city late kills the schedule, and on a flip the schedule is the margin.
Neil and Maggie walk a Waveland Park two-story with a new kitchen layout, a panel upgrade, a water heater, and a basement bath. At about $2,400 a month in carrying costs, three weeks of permit and inspection delay takes roughly $1,650 out of the spread.
The answer is not a bigger loan. It is putting the city on your schedule like any other trade, before you make the offer, and tying contractor payments to passed inspections instead of promises.
You will also hear the story of a veteran investor whose contractor vanished halfway through an eight-week job, and why he lost time but not cash.
In This Episode, You'll Learn:
- How to find out what your address needs for permits before you finalize the scope
- How to sequence rough-in inspections so the drywall crew never boxes you in
- How to price a failed inspection into your rehab budget before it happens
- How to pay contractors against passed inspections so you never get ahead of the work
- How to spot unpermitted work you could inherit and put the cost in your offer
- And more.
Hosted by Iowa real estate investor Neil Timmins.
Want the written breakdown? Look for the article "Flip Permits and Inspections in Iowa: What Slows a Project Down" at
https://littleguyloans.com
Find every episode at https://www.flippingiowa.com
Ready to fund your next flip? Little Guy Loans gets Iowa house flippers fast, flexible financing. Get funded today.
Episode 27
Two Failed Inspections and a Contractor Who Vanished
[MAGGIE] Two failed inspections and one late permit. Neil, how many weeks is that on a typical rehab?
[NEIL] Three. Maybe four if the inspector's calendar is ugly.
[MAGGIE] And at twenty-four hundred dollars a month in carrying costs, what does three weeks cost?
[NEIL] About sixteen hundred dollars. For doing nothing. Just waiting on somebody with a clipboard.
[MAGGIE] That's the part nobody puts in the pro forma.
[MAGGIE] Welcome back to Flipping Iowa. I'm Maggie, and I'm here with Neil. Neil, I keep running into flippers who tell me the city killed their schedule. Permits, inspectors, the whole thing. Is the city really the villain here?
[NEIL] Not usually. The city does what the city does. The villain is finding out about it late.
[MAGGIE] Late like when the electrician is already standing in the kitchen.
[NEIL] Exactly that. Contractor says the kitchen is two weeks out. Electrician walks in, looks at the panel, and says it won't pass. Now the whole schedule slides. And nobody did anything wrong. Nobody just asked the city what it needed to see first.
[MAGGIE] Okay, so for anyone listening who has a deal in mind for this fall, what are we covering today?
[NEIL] Three things. What actually needs a permit. Where the time really goes. And how to put the city on your schedule like any other trade, so a good margin doesn't turn into a thin one.
[MAGGIE] And you're saying permits rarely sink a deal by themselves.
[NEIL] Rarely. They sink the schedule. And on a flip, the schedule is the margin.
[MAGGIE] Let's start with the setup. Why does this trip up so many people, especially on a first or second flip?
[NEIL] Because the budget gets built around materials and labor. Cabinets, flooring, paint. Those are the things you can see. Permits feel like paperwork, so they get pushed to the bottom of the list.
[MAGGIE] So the plan has a line for the dumpster but not a line for the inspector.
[NEIL] Right. And then reality shows up. Here's the thing. Every city in the metro runs its own permit office. Des Moines, West Des Moines, Ankeny, Urbandale. Different forms. Different fees. Different wait times.
[MAGGIE] So there's no single Iowa checklist.
[NEIL] No. Anybody who hands you one is guessing. What holds almost everywhere is a pattern, and the pattern is what I want people to learn.
[MAGGIE] So if someone skips learning the pattern, that's where the weeks go. Has that actually happened to you?
[NEIL] More times than I can count. Early on, I'd walk a house, price the work, make the offer, and not call the city until demo was done. I paid for that every time. Now the call happens before the offer.
[MAGGIE] Before the offer. Not after you own it.
[NEIL] Before. Because what the city tells you changes what the house is worth to you.
[MAGGIE] Okay. Walk me through the pattern. What usually needs a permit?
[NEIL] Start with anything structural. Take out a wall, move a wall, open up a doorway. That usually needs a permit and an inspection.
[MAGGIE] That one I think most people know.
[NEIL] They know it for the big stuff. Then the trades. Electrical, plumbing, and mechanical. Electrical is a new panel or added circuits. Plumbing is a new bathroom or a re-pipe. Mechanical is a furnace, an air conditioner, or even a water heater swap. Those usually need both a permit and an inspection.
[MAGGIE] A water heater swap. People think of that as a Saturday job.
[NEIL] It is a Saturday job. It can still need a permit. That's the one that catches people.
[MAGGIE] And what typically doesn't need one?
[NEIL] Paint. Flooring. Swapping cabinets. Those usually don't. Then you've got the gray area, roofing, windows, decks. Those can go either way depending on the city and the scope.
[MAGGIE] So how does somebody find out which way it goes for their address?
[NEIL] Pick up the phone. Call the permit office for the city where the property sits. Do it before you finalize the scope of work. Ask what each line item needs, and ask how long they're running on reviews right now.
[MAGGIE] That's a five minute call.
[NEIL] Five minutes on the phone beats five weeks of guessing. I say that to every borrower.
[MAGGIE] Let me push on something. You said the delay isn't really the permit itself. If it's not the permit, where does the time go?
[NEIL] Three places. The review queue, inspection scheduling, and failed inspections. Let's take them one at a time.
[MAGGIE] Review queue first.
[NEIL] Some permits come back fast. Others just sit. And the clock only starts once you submit a complete application. Miss a contractor license number, hand them an unclear sketch, and the clock restarts.
[MAGGIE] So a sloppy application is the same as not applying.
[NEIL] Close to it. You lose the days you waited, and you start over. The fix is boring. Have your contractor's license information ready. Draw a clean sketch. Read the form twice.
[MAGGIE] Okay. Second one. Inspection scheduling.
[NEIL] This is where flippers get hurt. A rough-in inspection has to happen before the walls close up. The inspector looks at the wiring, the pipes, before the drywall goes on.
[MAGGIE] And the drywall crew is booked.
[NEIL] That's the squeeze. Drywall crew says Monday. Inspector can't get there until Wednesday. So you either wait two days, or you gamble.
[MAGGIE] What does gambling look like?
[NEIL] You tell the crew to hang it anyway and hope nobody asks. Don't. If you cover work before it's inspected, the usual result is tearing it back out. Now you've paid for drywall twice and you still wait for the inspector.
[MAGGIE] That sounds like a very expensive Wednesday.
[NEIL] It's the most expensive Wednesday in the business.
[MAGGIE] So the third one, failed inspections. I'd guess this is the one that stacks.
[NEIL] It stacks. Think about the steps. A failed inspection means the fix. Then the call to get re-inspected. Then the wait for the next opening. Then the trade has to come back, and their calendar isn't your calendar.
[MAGGIE] So a small fix isn't a small delay.
[NEIL] A tiny fix can cost a week or more. Each step depends on the one before it. A missing smoke detector can take ten minutes to fix and nine days to clear.
[MAGGIE] Let's put some real numbers on this. Can we walk a deal?
[NEIL] Sure. Say you're buying a two-story in Waveland Park. Nice street, good bones. Your scope has a new kitchen layout, a panel upgrade, a new water heater, and a bathroom added in the basement.
[MAGGIE] That's a pretty normal scope for the area.
[NEIL] It's very normal. And every item on it touches a permit. Electrical, plumbing, mechanical. So here's how I'd sequence it so the inspections don't box you in.
[MAGGIE] Go ahead.
[NEIL] Step one, pull the permits for the electrical, plumbing, and mechanical work before demo starts. Not during. Before.
[MAGGIE] Why before?
[NEIL] Because the review queue is running while you're doing other things. If you pull them first, that wait overlaps with your demo. If you wait, that wait comes after your demo, and now nothing happens on the job.
[MAGGIE] So you're using their delay time for your own work.
[NEIL] That's it. Step two, finish demo and do the rough-ins. The panel, the new circuits, the basement bath plumbing.
[MAGGIE] Then the inspections.
[NEIL] Then you schedule each rough-in inspection, and here's the rule. The drywall crew waits until each one passes. Not until the inspector is scheduled. Until it passes.
[MAGGIE] That's a hard rule to hold when the drywall guy is standing there with his truck.
[NEIL] It is. Hold it anyway. Step four, if anything gets flagged, you fix it, you call for re-inspection, and only then do the walls close. And step five, book the final inspections while the trades are wrapping up. Not after the house is staged.
[MAGGIE] Not after the house is staged. I can picture someone with a couch in the living room and the inspector calling to say he can't come until Thursday week.
[NEIL] I've seen that exact picture.
[MAGGIE] Okay, so put a price on it. What does all this slipping actually cost on that Waveland Park house?
[NEIL] Take carrying costs at about twenty-four hundred dollars a month. Interest, taxes, insurance, utilities. That's roughly five hundred fifty dollars a week.
[MAGGIE] Five hundred fifty a week just to own it.
[NEIL] Every week it sits. Now two failed inspections and one late permit can easily cost you three weeks. That's about sixteen hundred fifty dollars out of the spread. And that's before the trade has to come back for a second visit.
[MAGGIE] So you worked hard to protect that spread when you set your offer, and a permit slip takes a chunk of it.
[NEIL] A chunk. Not the whole thing. But that's the point. Nobody's deal dies from one failed inspection. They die from a few of them, stacked with a contractor who wanders off, stacked with a surprise.
[MAGGIE] Let's talk about the surprise that isn't your fault. Unpermitted work you inherit.
[NEIL] This one's sneaky. You buy a house with a finished basement or a deck. The last owner built it without a permit. You don't find out until a buyer's inspector asks questions, or a lender looks closer.
[MAGGIE] And by then you own it.
[NEIL] By then you own the problem. So when you walk a house, look for work that seems newer than the permit history suggests. Then ask the city what's on file for that address.
[MAGGIE] What do you do if you find something?
[NEIL] You price in the cost of bringing it up to code before you make the offer. Not after. If a basement bedroom has no egress window and no permit, that's a number. Put the number in your offer.
[MAGGIE] So the offer absorbs the surprise, instead of your margin absorbing it.
[NEIL] Right.
[MAGGIE] Now, the fix you keep coming back to. Put permits and inspections in writing.
[NEIL] In the scope of work. Before the first dumpster shows up. Name who pulls each permit. Licensed trade contractors often pull their own, but confirm it in the contract.
[MAGGIE] Because assuming is how nobody pulls it.
[NEIL] Because everybody thinks somebody else did. Then ask for the permit numbers and keep copies in your project folder.
[MAGGIE] What else goes in the scope?
[NEIL] Each inspection becomes a milestone on the schedule. With a buffer day on either side. And budget for permit fees and a possible re-inspection right in your rehab number.
[MAGGIE] So you plan on the failed inspection instead of hoping it doesn't happen.
[NEIL] Plan for one. If you get zero, great. You've got a little cushion.
[MAGGIE] And if you're managing the crew yourself?
[NEIL] Walk the site before every inspection. Take photos. If something looks off to you, it'll look off to the inspector. Always have a written scope, and always be on site.
[MAGGIE] Neil, I want to bring in the money side, because I think a lot of people tune out when it turns into financing.
[NEIL] Fair. Here's how it ties together. Our loans go up to ninety percent of the purchase price, up to one hundred percent of rehab costs, and a maximum of seventy percent of after repair value. That seventy percent is the controlling cap.
[MAGGIE] So even if the rehab dollars are covered, the cap is the cap.
[NEIL] Right. And because the cap controls, a permit delay or a failed inspection doesn't get fixed with a bigger loan. It comes out of your margin. That's why I want the permit and re-inspection costs in the rehab budget from day one. The scope you finance should match the scope you build.
[MAGGIE] And approvals move quickly on your side. Twenty-four hours, close in as little as five days.
[NEIL] Which is great. But a fast close doesn't help if the schedule after the close is guesswork. Speed on the front end, planning on the back end.
[MAGGIE] Neil, earlier you mentioned tying contractor payments to passed inspections, not just finished work. That feels like it connects to a story you've told me before about a contractor who disappeared.
[NEIL] It does. This one's about an investor who's been around a long time. Flipped a lot of properties. Knows what he's doing.
[MAGGIE] So not a rookie.
[NEIL] Not even close. He brings on a new contractor for an eight week project. Four weeks in, the contractor is gone. Completely. No call. No text. No explanation. Nobody who knew where he went.
[MAGGIE] Four weeks in, so halfway through the job.
[NEIL] Halfway. Project is sitting half-done. Nobody on site. A week goes by with nothing. Then another.
[MAGGIE] Okay, I'm going to say what I'd be thinking. That investor is out a pile of money.
[NEIL] That's what you'd expect. But he wasn't. He lost time. He did not lose cash.
[MAGGIE] Why not?
[NEIL] Because he knew the one rule that separates experienced operators from the ones who get burned. Never let the contractor get ahead of you. You always want to owe them money.
[MAGGIE] Wait, walk me through that. You want to owe your contractor?
[NEIL] At every point in the project. The contractor should have done more work than what he's been paid for. You agree on milestones up front and you pay against completed work. Not against promises.
[MAGGIE] So if someone skips that and writes a big check on day one, that's where the money goes.
[NEIL] That's exactly where it goes. The contractor says he needs half up front to get started. The investor writes the check. The contractor disappears with it. Now the project stalls and the investor is out of pocket and hunting for someone to finish a half-started job.
[MAGGIE] And the investor in your story?
[NEIL] He was behind on payments by design. The contractor hadn't been fronted anything significant. So when the guy vanished, there was no unearned check sitting out there. The investor found another contractor, got them in, finished the project. He lost time on the timeline, and that's not nothing when the interest clock is running. But he kept his cash.
[MAGGIE] Lost time, not lost money. Neil, that's the sentence I'd put on a sticky note.
[NEIL] You can't always stop a contractor from walking off. You can control whether he walks off with your money.
[MAGGIE] Now connect it back to permits. Where do inspections fit in that payment structure?
[NEIL] Right in the middle of it. A passed inspection is the cleanest milestone you will ever get. It's a third party saying the work is done and done right. So I like to tie a payment to it.
[MAGGIE] So the rough-in gets paid when the rough-in inspection passes.
[NEIL] Yes. Not when the electrician says he's finished. When the city says it passed. That protects you two ways. The contractor has a reason to get the work right the first time, because he doesn't get paid until it clears. And you never fund work that has to be torn out.
[MAGGIE] That also keeps him from getting ahead of you without you having to fight about it.
[NEIL] Right. The structure does the arguing for you.
[MAGGIE] Okay, I want to bring in a listener objection. I know somebody out there is thinking, this is a lot of process. I'm a one-man operation. Do I really need to call the city and write all this down before I make an offer?
[NEIL] I get it. It does feel like extra work. But think about what you're comparing it to. A five minute call, a one page scope, and a couple of extra lines in a spreadsheet. Against three weeks of carrying costs and maybe tearing out drywall.
[MAGGIE] So the process is cheaper than the mistake.
[NEIL] By a lot. And honestly, the process gets faster each time. The second deal in a city, you already know who to call. The fifth deal, you know the inspector by name.
[MAGGIE] That's a good point. The city gets less mysterious.
[NEIL] It becomes another trade. You know their schedule, you know what they want to see, and you plan around it.
[MAGGIE] Another one I hear. What if the permit office is slow right now and there's nothing I can do?
[NEIL] Then you build that into the offer. If the review is running three weeks, your timeline is three weeks longer, and your carry is higher. If that kills the deal, better to know before you buy than after.
[MAGGIE] So a slow permit office isn't a reason to skip the call. It's a reason to make the call.
[NEIL] Yes. Information is the whole game.
[MAGGIE] And one more. Can I start demo before the permit comes through?
[NEIL] Some interior demo doesn't need a permit and some does. It depends on what you're removing. Ask the permit office first. Tearing out the wrong wall early can cost you more than waiting a few days.
[MAGGIE] That one stings because demo feels like progress.
[NEIL] It feels like progress. Sometimes it's just a fine.
[MAGGIE] Before we wrap, I want to do the history beat. You've got one for us.
[NEIL] I do. This one's about aluminum. On December sixth, eighteen eighty-four, workers set a one hundred ounce piece of aluminum on top of the Washington Monument. At the time, aluminum cost about what silver did.
[MAGGIE] Aluminum. The stuff in a soda can.
[NEIL] The stuff you toss in a recycling bin now. Two years later, a new refining process made it cheap. Nothing about the metal changed. Just how easy it was to get.
[MAGGIE] So the same material went from precious to disposable in two years, just because someone figured out a better way to produce it.
[NEIL] That's it. So next time a contractor tells you a material is hard to find and pricey, remember that's usually a snapshot, not a permanent condition. Same with a permit office. A three week review today might look different next season.
[MAGGIE] Which is a good reminder to ask, and to keep asking. Okay, Neil, let's land this. If someone only remembers a few things from today, what are they?
[NEIL] One. Call the city before you finalize your scope, and before you make the offer. Two. Put every permit and every inspection on the schedule, name who pulls each one, and tie contractor payments to passed inspections. Three. Keep a buffer in your carrying costs for one failed inspection.
[MAGGIE] So call the city, put the inspections on the calendar, and plan for a failed one.
[NEIL] The investors who finish on time aren't lucky. They treat the city as another trade on the job and they plan around it.
[MAGGIE] Do that on the next deal, and the schedule you promised yourself starts to hold. Neil, thanks for walking us through it.
[NEIL] Always a good one, Maggie. And thanks to everybody listening. Go make that phone call.
[MAGGIE] If you got something out of this one, share it with a friend who's working on a flip, and be sure to subscribe so you don't miss the next one. Catch you on the next episode.
Audible
iHeartRadio
Amazon Music 